Commercial Strategy

I stabilise the commercial engine from day one linking scope, programme and cost into one version of the truth. Expect tighter change control, clearer interfaces, and a month‑end that protects cash (valuations, Pay‑Less, WIP, CVR). Built for NEC/JCT/FIDIC delivery, with actions that move numbers in the first reporting cycle.

FAQs

When does an assumption become a change?

When it remains unproven at contract signature and later proves false, or when a client decision/date slips beyond the basis of estimate, capture via CE/VO with trigger and evidence.